Stockpiles
On 26 September 2023, Court Orders were made in settlement of the Environment, Resources and Development Court proceedings. Those Orders required Neutrog to reconfigure its stockpile dimensions to 3m (H) x 7m (W) x 25m (L) to align with the current development approval and relevant EPA licence condition. The Orders reversed the EPA’s decision to issue an Environment Protection Order (EPO), noting that the reconfiguration of the stockpiles was the primary purpose for the EPO being issued.
The EPA is monitoring Neutrog’s compliance with these Court Orders.